California University of Pennsylvania Stanley Hall

The demolition of Stanley Hall, located on the California University Campus, was performed to make room for new future student housing. Advanced Builders, completed the entire scope of work in 63 calendar days, including the asbestos abatement of all seven floors. This project was completed in advance of the scheduled completion date and was the fourth building demolished on the CUP Campus, by our team.

California University of Pennsylvania Stanley Hall photo

  • ClientCalifornia University of Pennsylvania
  • LocationCalifornia, PA
  • Value$319,000
  • Highlights
    • Demolition and environmental remediation of Stanley Hall, a seven story student housing complex
    • Demolished and removed in its entirety, 88,000 sf of building, including below grade slabs and columns, along with utility disconnects
    • Rough grade to existing contours, seeded and mulched the entire site