Murdoch Building

Demolition of a 2 story once parking garage down to grade including removal of the floor slab on grade and foundation walls to two feet below grade. The concrete floor was broken in the basement area and backfilled with crushed concrete recycled from the structure. All structural steel and reinforcing bars within the concrete were recycled offsite. The site was then covered in fill and capped with topsoil, graded, seeded, and mulched. The site conditions were less than optimal due to the close proximity of neighboring structures and the congestion of both vehicular and pedestrian traffic.

Murdoch Building photo

  • ClientTurner Construction Co.
  • Location3440 Forbes Ave., Pittsburgh, PA
  • Value$363,400 plus salvage
  • Highlights
    • Demolition of a 2 story once parking garage converted to office and retail space located in the heart of Oakland in downtown Pittsburgh.
    • Building materials consisted of thick heavily reinforced concrete slabs and pillars.
    • The structure was only inches away from the new Hilton Garden Inn Hotel on Forbes Avenue.